Background and constraints
A fictional indoor scavenger activity for 30 people begins 15 minutes late. The venue must still close at 17:00, and the organizer needs an honest revised schedule.
Exact inputs
Start: 15:15. Available duration: 105 minutes.
Rules, boundaries and access briefing | 15 Team setup | 10 Main hunt | 45 Evidence verification | 15 Closing and cleanup | 20
Actual calculated running order
| Activity | Start | End | Minutes |
|---|---|---|---|
| Rules, boundaries and access briefing | 15:15 | 15:30 | 15 |
| Team setup | 15:30 | 15:40 | 10 |
| Main hunt | 15:40 | 16:25 | 45 |
| Evidence verification | 16:25 | 16:40 | 15 |
| Closing and cleanup | 16:40 | 17:00 | 20 |
Total: 105 minutes. Remaining: 0 minutes. The entered schedule fits within the available duration.
Planning process
The host changes the start time and available duration together. The main hunt is reduced from its earlier 60-minute proposal to 45 minutes by removing two optional tasks. The safety briefing and cleanup remain intact. Helpers receive the revised printed times before teams begin.
Result explanation
The recalculated order closes at 17:00. Starting later without reducing the available duration would simply move the problem into the next booking. Reducing task scope is more credible than expecting every team to travel and solve faster.
Alternative
Switch to a seated clue packet if setup is still incomplete at 15:15. A smaller activity with clear instructions is preferable to an improvised route.
Execution notes
Tell guests which tasks were removed and retain a fixed return cue. Never use a late start as a reason to omit boundaries or access information.
Continue planning
How to Plan a Scavenger Hunt for Groups
Leaving a Visible Buffer in a Creative Workshop
FAQ
Does this check my venue calendar?
No. It compares entered segment durations with the entered limit; it does not access external bookings.
What happens when a segment changes?
After the first calculation, edits to the inputs recalculate later times. Review any conflict warning and save the revised plan.